This contract on behalf of Stockton Borough Council comprised of internal remodelling and refurbishment to the main halls and resource area to an accelerated programme during the 6 week school summer holiday period. The works involved removing the existing ceilings and accoustic wall coverings from the main hall and surrounding rooms to insert very large pieces and a complex steelwork frame adjoining to the existing school structure. The purpose being to enlarge the existing hall and make use of the 2nd hall converting this into another classroom.

Once the new steelwork frame is set into place new ceilings and dividing walls will be formed and new mechanical and electrical installations carried out. New fittings will include 2 new veluxe roof windows, glass block wall, new doors, ironmongery, paint and floor finishes throughout.